MV “Marlin Ametrine”, the 3rd vessel of Marlin series that undertook EGCS retrofit under SMC’s supervision, successfully completed its EGCS retrofit in 21 days and sailed away on 21st May, following EGCS retrofit of the leading vessel, MV “Marlin Ammolite”, which was delivered on 18th Jan.
Owner: TRAFIGURA MARITIME VENTURES LIMITED
Shipyard: COSCO SHIPING SHIPYARD (NANTONG) CO., LTD
Scrubber maker: ALFA LAVA
EGCS Type: Open Loop
The vessel berthed on 26th April 2020, completed all retrofit jobs on 17th May (total 21days), completed commissioning with DNVGL surveyor’s satisfactory on 20th May, and have got the short term IAPP certificate.
All works smoothly finished within 25 days as per initial request from Owner, the vessel was successfully delivered with Owner’s satisfactory. Then as remote survey by DNVGL accepted, SAT was successfully completed at 17:30 LT, 24 May 2020 by ship’s crew themselves and confirmed all in good order.