SMC 뉴스
Company Announcement
We take pleasure in announcing that Steve Nolan has been promoted to the position of Technical Director at Schulte Marine Concept. The appointment comes as the recognition of Steve’s experience and knowledge, uncompromised commitment and dedication to company, recognition and promotion of corporate culture, fantastic team work spirit, mentoring and coaching attitude, implausible performance capacity and capability, …, all very rare commodities in this world.
Launching of mv “Molly Schulte”
SMC is pleased to report Launching Ceremony in Zhejiang East Coast Shipbuilding Co., Ltd, China (Yangfan Shipyard): of mv “Molly Schulte”, Hull No.CV23H BS10, the tenth unit from the series of 12 x 2339 TEU Container carrier ordered by Bernard Schulte & J.P Morgan.
Vessel’s principal particulars: LOA = 188.85m, B = 30.4m, D = 16.9m, T d/s = 8.50/10.5m. Propelled by MAN B&W 6G60ME-C9.2 Tier II and developing 11,556KW x 93.7 rpm at NCR the vessel will operate at the speed of 18.93 knots. All vessels in the series are classed by Lloyd’s Register and will be built to Singapore flag requirements.
Classification notes: “100A1 Container Ship, Ship Right (SDA, FDA plus(25 N/A), ACS(B), CM), LI, *IWS, ECO (IHM, EEDI-3) +LMC, UMS, NAV1 Descriptive Notes: ShipRight(SCM, SERS, (BWMP(T)).
Delivery of the vessel is scheduled for end of Sept 2017.
Keel laying of mv “PACIFIC UNITY”
SMC is pleased to report Keel laying in Shanghai Waigaoqiao Shipbuilding Co., Ltd., China: of mv “PACIFIC UNITY”, Hull No. H1445, the first unit from the series of 4 x 400,000 DWT VLOC ordered by HONGKONG MING WAH SHIPPING Co., Ltd.
Vessel’s principal particulars: LOA = 362.0m, B = 65m, D = 30.4m, T d/s = 23m. Propelled by MAN B&W 7G80ME-C9.5 With Low Load EGB TII and developing 20,570 KW x 54.9 rpm at NCR the vessel will operate at the speed of 14.5 knots. All vessels in the series are classed by DNV-GL & CCS and will be built to Hongkong flag requirements.
Classification notes: 1A1 Ore Carrier NAUTICUS (Newbuilding) CSA-2 IB-3 NAUT-OC EO TMON BIS Gas ready (D,S, MEc,) BWM-E(s) COAT-PSPC(B,D) EL-2 HMON(G4, C1, W1, O1, A1, S1, E1) SHORE POWER BWM(T) CLEAN OPP-F.
Delivery of the vessel is scheduled for 10th March 2018.
Delivery of mv “INTERLINK NOBILITY”
SMC is pleased to report Ship Delivery in M/s. Taizhou Kouan Shipbuilding Co. Ltd, China: of mv “INTERLINK NOBILITY”, Hull No. TK1018, the eleventh unit from the series of 13 X GREEN DOLPHIN 38,800 DWT Bulk Carriers ordered by Marine Capital Corporation, Bermuda.
Vessel’s principal particulars: LOA = 180.0 m, B = 32.0 m, D = 15.0 m, T d/s = 9.5/10.5 m. Propelled by MAN 5S50ME-B9.3 Tier II engine and developing 4575 KW x 89.9 rpm at CSR the vessel will operate at the speed of 14 knots at 9.50 draft. All vessels in the series are classed by Lloyd’s Register and will be built to Marshall Islands flag requirements.
Classification notes: LR +100A1 Bulk Carrier, CSR, BC-A, Hold Nos. 2, 4 may be empty, Grab [20], ESP, Ship Right (CM, ACS(B,D)), *IWS, LI, ECO(P, BWT, EEDI, IHM), Ice Class 1C FS. + LMC, UMS; With Descriptive notes: Ship Right ((BWMP (F,T), SCM, SERS).
The construction commenced with Steel Cutting on 22nd April 2014 followed by the erection starting in slipway on 25th July 2016. The Ship launched on 18th Oct 2016 and the sea trial completed successfully on 10th June 2017. BSM, HK took delivery of ship after Delivery Signing Ceremony on 22nd June 2017 which is attended by Ship Owners, Class Surveyors, SMC and Shipyard representatives.”
The ship is scheduled to sail out from shipyard on 23rd June 2017. Will send more photos by separate emails tomorrow.
Steel cutting of the 2nd VLOC in SWS
SMC is pleased to report Steel Cutting in Shanghai Waigaoqiao Shipbuilding Co., Ltd., China: of mv “PACIFIC UNITY”, Hull No. H1446, the second unit from the series of 4 x 400,000 DWT VLOC ordered by HONGKONG MING WAH SHIPPING Co., Ltd.
All vessels in the series are classed by DNV-GL & CCS and will be built to Hong Kong flag requirements.
Delivery of the vessel is scheduled for 28th June 2018.
A great vessel does not build itself
Building a new vessel type, full of innovative approaches is a challenge already. Adding the fact that it is built parallel at two yards under significant time pressure does not make it any easier.
In January 2015, Hamburg shipping company, Bernhard Schulte and Siemens signed a charter contract for two so-called Service Operation Vessels (SOV) to facilitate maintenance of offshore wind farms. After signing, there were only 18 months left to build this prototype vessel – and the final drawings were not even in place yet. This next generation of SOVs was jointly designed by Bernhard Schulte Offshore and Ulstein Design & Solutions according to the specific requirements provided by Siemens Windpower. 40 service technicians can live comfortably onboard the SOV in single cabins while out in the wind farm and can go to work daily from the vessel to the turbine and back via a motion compensated gangway.
To ensure a safe transfer of service technicians via the gangway and the SOV’s fast re-positioning between the turbines, the vessel’s hull has been optimised for Dynamic Positioning (DP). The highly efficient optimisation was achieved with the X-BOW design and pioneering application of the X-STERN design, providing the vessel with unique astern operational capability and capacity against wind and waves, equal to heading performance. Praxis-orientated logistical flows allow for the first time that spare parts and equipment can be transported with a trolley from the SOV’s warehouse under weather deck via an elevator to the upper deck and over the motion compensated gangway onto the wind turbine.
Bernhard Schulte Offshore called for tenders among 25 yards worldwide to locate the right yard to design and build the two vessels. Besides commercial aspects and references of similar vessel builds, the design capability and capacity, workmanship quality, efficient and detailed project planning by the yard were intensively audited. This is where Schulte Marine Concept (SMC) first came into play. The team of highly qualified naval architects and marine engineers visited multiple yards. They reviewed the yards’design, production, planning processes and looked closely at the vessels being built there. Finally, the chosen yard was the Ulstein yard in Norway which convinced with its far-reaching knowledge and experience in building prototypes. Nonetheless, the hulls of both SOVs were built and partly equipped at the Crist yard in Poland to optimize the project’s execution schedule and budget.
Ulstein developed in record time the final design and invited the owners to come and take receipt of the plans and to conclude on the makers’ selection process. SMC was continuously available to Bernhard Schulte Offshore as a technical consultant and providing abundant knowledge from previous offshore newbuilding projects. Using a digital 3D-model of the ship the hull structure, vessel’s equipment, systems and furnishings were checked in regard to design coordination and vessel’s safe and efficient operation and maintenance, ensuring a high level of durability and operational reliability. On the 20th April 2015, under the supervision of SMC, the steel cutting for the hull began in Crist yard, Gdynia. In record time, the complete prefabrication of the first blocks was completed and only three months later the hull erection in the dry-dock commenced. A team from SMC was continuously at the construction site supervising the construction works, ensuring contractual compliance while observing closely that the respective regulations and rules were adhered to. All design, construction, performance non-conformities were immediately addressed to the builder, corrective as well as preventive actions agreed and implemented. The owner was kept thoroughly informed about the SOV’s construction and commissioning with regular detailed reports. In December 2015, the first hull left the Crist yard and was towed to Norway. During the journey an unusually strong storm came over, forcing the SOV and the tug to seek shelter at the port of Kristiansand and to spend Christmas there. On the 3rd of January, the hull finally arrived in the dock at Ulstein yard in Ulsteinvik. Here, the second team from SMC took over supervision duties, overseeing the further construction and outfitting works, including the installation of the entire propulsion system, bridge equipment and the interior fittings for the accommodation area. Even though a Norwegian yard stands for high quality, there are always some challenges involved when working on a prototype vessel in combination with so many new components (Siemens BlueDrive C, Uptime Gangway, MT integrated bridge & DP system, etc.). With the site manager from SMC at the yard there was always a representative on site, who could foresee problems earlier and could discuss the matters with the yard’s project manager directly to find quick and commercially sound solutions without delaying the building time schedule.
Beginning of June 2016, WINDEA LA COUR embarked on a test sail, while the Polish built hull from WINDEA LEIBNIZ arrived in Norway. SMC assisted the owner during the delivery of the first vessel from the yard. Menwhile, SMC ensured that the corrections from the first vessel would also be implemented on the second ship. SMC employees were also on board the vessel during the operational testing in the wind farm to gather the first operational experiences. The experience gained at the wind farm was integrated into the second vessel to enhance the operability even further. In February 2017, WINDEA LEIBNIZ was delivered to Bernhard Schulte and with it the 423rd newbuilding project for SMC was successfully completed. Matthias Müller, managing director of Bernhard Schulte Offshore, draws a positive résumé: SMC guided us safely through the building process and together with the Ulstein yard ensured that we can start our charter contract on time. SMC did not only make sure that the yard strictly complies with the building plans, but they also ensured that the vessel could perform the manoeuvres as per the charter contract requirements.
Schulte Marine Concept (SMC) provides a comprehensive range of technical and project management services for newbuilding, conversion and retrofit projects as well as technical support for the fleet in service. SMC’s project tailored services range from design consultancy, project feasibility studies, through shipyard audits, shipbuilding contract and technical specification negotiations, plan approval and 3D model review, construction site supervision to ship inspections, dry docking support and ballast water treatment retrofits. Today, in April 2017 SMC is working on the 447th new-building project.
The free CSS minimizer will compress the style files for your websites in seconds and it does not require download and installation.
Launching of mv ”Spil Hayu”
SMC is pleased to report Launching Ceremony in Nanjing Dong Ze Shipbuilding, China: of mv ”Spil Hayu”, Hull No. Dz-55, the forth unit from the series of 4 x 900 TEU Container vessel ordered by Asia Pacific Shipmanagement Pte Ltd.
Vessel’s principal particulars: LOA = 135.70m, B = 22.50m, D = 10.2m, T d/s = 5.6m. Propelled by MAN 5S35MC-C9.2 developing 2975 kW x 142 rpm at NCR the vessel will operate at the speed of 12.5 knots. All vessels in the series are classed by Chinese Class Society and was built to Indonesian flag requirements.
Classification notes: CSAD Container Ship; Greater Coastal Service; Loading Computer (S,I,D); In-Water Survey; CSM MCC
Delivery of the vessel is scheduled for 30th July 2017.
Delivery of mv “INTERLINK FORTUITY”
SMC is pleased to report Ship Delivery in Taizhou Kouan Shipbuilding Co. Ltd, China: of mv “INTERLINK FORTUITY”, Hull No. TK1017, the tenth unit from the series of 13 X GREEN DOLPHIN 38,800 DWT Bulk Carriers ordered by Marine Capital Corporation, Bermuda.
Vessel’s principal particulars: LOA = 180.0 m, B = 32.0 m, D = 15.0 m, T d/s = 9.5/10.5 m. Propelled by MAN 5S50ME-B9.3 Tier II engine and developing 4575 KW x 89.9 rpm at CSR the vessel will operate at the speed of 14 knots at 9.50 draft. All vessels in the series are classed by Lloyd’s Register and will be built to Marshall Islands flag requirements.
Classification notes: LR +100A1 Bulk Carrier, CSR, BC-A, Hold Nos. 2, 4 may be empty, Grab [20], ESP, Ship Right (CM, ACS(B,D)), *IWS, LI, ECO(P, BWT, EEDI, IHM), Ice Class 1C FS. + LMC, UMS; With Descriptive notes: Ship Right ((BWMP (F,T), SCM, SERS).
The construction commenced with Steel Cutting on 02nd March 2015 followed by the erection starting in slipway on 26th Jan 2016. The Ship launched on 14th May 2016 and the sea trial completed successfully on 19th April 2017. BSM, HK took delivery of ship after Delivery Signing Ceremony on 18th May 2017 which is attended by Ship Owners, Class Surveyors, SMC and Shipyard representatives.”
The ship is scheduled to sail out from shipyard on 19th May 2017.
Steel cutting of the 3rd and 4th VLOC in Yangzi Xinfu
SMC is pleased to report the Massive Steel Cutting Ceremony in Yangzi Xinfu Shipbuilding Co., Ltd, China of mv “ORE NINGBO” (Hull No. YZJ2015-2277) and “ORE HONGKONG” (Hull No. YZJ2015-2272), the third and fourth unit from the series of 6 x 400,000 DWT Ore Carrier ordered by ICBC Leasing and HKMW.
The vessel is classed by CCS and will be built to Hongkong flag requirements.
Contract delivery of the vessel is scheduled for October 31st, 2018 / November 30th, 2018.
Delivery of mv “ZITA SCHULTE”
SMC is pleased to report Delivery in STX Offshore & Shipbuilding, Korea: of mv “ZITA SCHULTE”, Hull No. S4035, the fifth unit from the series of 6 x 12 000 m3 ethylene/LPG/NH3/VCM gas carrier ordered by Ultragas-Europe.
Vessel’s principal particulars: LOA = 146.20m, B = 22.60m, D = 12.10m, T d/s = 7.40/9.30m. Propelled by STX MAN 6S40ME-B9.1 and developing 6,129 KW x 141 rpm at NCR the vessel will operate at the speed of 16.4 knots. All vessels in the series are classed by DnV.GL and will be built to Isle of Man flag requirements.
Classification notes: +1A1 Tanker for liquefied gas, Ship type 2G (-104 deg C, 972 Kg/m3, 5.0 bar), E0, TMON, BIS, COAT-PSPC(B), BWM-E(S) & BWM-T, ICE-C1.
The vessel will be chartered by UNIGAS POOL PARTNERS.