Delivery of mv “INTERLINK SOLIDITY”
8 8 月, 2017Honorary certificate for SMC site team issued by SWS
16 8 月, 2017Delivery of mv ”Mimmi Schulte”
SMC is pleased to report Delivery Ceremony in Zhejiang East Coast Shipbuilding Co., Ltd, China (Yangfan Shipyard): of mv “Mimmi Schulte”, Hull No.CV23H BS09, the ninth unit from the series of 12 x 2339 TEU Container carrier ordered by Bernard Schulte & J.P.Morgan. Vessel’s principal particulars: LOA = 188.85m, B = 30.4m, D = 16.9m, T d/s = 8.50/10.5m. Propelled by MAN B&W 6G60ME-C9.2 Tier II and developing 11,556KW x 93.7 rpm at NCR the vessel will operate at the speed of 18.93 knots. All vessels in the series are classed by Lloyd’s Register and will be built to Singapore flag requirements. Classification notes: (LR) “100A1 Container Ship, Ship Right (SDA, FDA plus(25 N/A), ACS(B), CM), LI, *IWS, ECO (IHM, EEDI-3) +LMC, UMS, NAV1 Descriptive Notes: ShipRight(SCM, SERS, (BWMP(T)) Vessel supervision was taken over by SMC at the start of construction schedule – on 5th of May 2015.
Following are milestone points
1) Steel cutting – 5th May 2015
2) Keel Laying – 11th Jan. 2016
3) Launching – 5th March 2017
4) Sea Trial – 21st to 24th July 2017
5) Delivery – 9th August 2017