• English
SMC-logo-website(1)SMC-logo-website(1)SMC-logo-website(1)SMC-logo-website(1)
  • COMPANY
    • Profile
    • Vision & Mission
    • Policies
    • Our Team
    • Schulte Group
    • Bernhard Schulte Shipmanagement
    • Corporate Leaflet
  • SERVICES
    • Newbuilding & Conversion Projects
    • Fleet in Service Support
    • Ballast Water Treatment System Retrofit
    • Scrubber Retrofit
    • FDD ACQUISITION SERVICES
  • PROJECTS
    • Current Projects
    • Track Record
    • Shipyard Experience
    • Client List
  • VACANCIES
  • NEWS
    • SMC News
    • SMC Videos
    • Highlights
  • CONTACTS
    • Contacts
✕
Erection of VLOC
June 26, 2018
Delivery of product/chemical tanker “Thames”
July 12, 2018

BWTS retrofit project

July 12, 2018

SMC is pleased to announce that we are continuing with Ballast Water Treatment System (BWTS) retrofit management. On 12th July 2018, SMC carried out survey for a 20,600 m3 LPG Carrier, “Immanuel Schulte” at the jetty in Tuticorin, India. During the survey, the following items have been inspected on board the vessel:

  • possible locations for the installation of the different components
  • tie-in locations into existing piping systems
  • wire routing, cable penetrations
  • main switchboard for available space for additional breakers

Forward part of the engine room (floor level and 3rd deck level) has been 3D scanned and proposal of possible lay-out and installation is under development.

The whole design process is expected to take 12 weeks, including Class approval process. All production documentation, including material specification, will be finished before the vessel’s drydocking scheduled for October 2018. Installation process of BWTS will be carried out by repair yard and supervised by SMC.

 
 